Jetty process

 
 


This process will start immediately after loading and discharging process, and will end after putting the cargo in uncovered or covered areas.

In this step cargos will be moved by some machines , workers ,register authorities from the place of hooks up to temporary substituting place. During this process usually a heavy traffic will occured.

The sublevels of harbor process of loading and discharging of import goods:

A).Arranging the shipment: This operation will be done on the vehicle which is stopped on the harbor and under hook more over counting and inspection of goods will be done.

B). Moving the trailer or low bed:
After loading the cargo on the vehicles, they'll be transshipped to the areas or warehouses.

C). Discharging of the cargo from low bed :

After placing the trailer or low bed in front of warehouse, the cargo will be checked and discharged.

D). Returning the trailer to the harbor:
After discharging trailers will return back to the harbor for reloading.